Transformation of the R&D site Schneider-Electric TECHNOPOLE, Grenoble, France
Schneider-Electric invests on the site Technopole to gather the "Energy" Business Unit (medium voltage) R&D teams enhancing internal synergies and major technology & innovation centers like CEA, Minatec, ST, Grenoble INP, etc
Project steps:
- Moving of about 300 persons outside of the site
- Demolition & asbest removal of 10000 sqm old building
- Networks, road & parking modification
- Construction of a new building of 17000 sqm
- Construction of 6500 sqm laboratory
- Moving of heavy and highly sensible electrical test systems into the new laboratory
- Moving of 950 persons into the new building
The project targets a LEED PLATINUM label and 45kWh/sqm /y energy efficiency
Packages:
1) Permitting & specification of the main building: Arche5
2) Studies: networks, laboratory, demolition etc: Ingerop
3) Main building & labs building: General contractor (GA)
4) Technical packages of the labs: 6 contractors
5) Demolition & Asbest removal: 1 contractor
6) Networks, road & parking: 1 contractor
Principal project data
Budget: 51,6 M Euros
Scope IPS
Project Feasibility
- Collection of the "needs"
- Definition of the program
- Roadmap
- Budget & planning
Project Preparation
- Coordination of the architect & study offices
- Definition of the packages
- Procurement
Project Realization
- Follow-up of the general contractors
- Follow-up of Study offices
- Detailed Planning
- Budget Management
- Transfert organisation
IPS operational unit(s)
- IPS Belgium sa
- IPS France SARL